Beginning of the year at the construction site

The beginning of the year was a very important and extremely intensive time at the construction site. The works connected with the construction of the diaphragm walls in the garage zone of the building have been completed and now they are being erected at the ‘caisson’ at the south side of the East-West route tunnel. In January, the erection of the wall caps on the diaphragm walls commenced. They bind all the walls peripherally and are an element of connection with the reinforced concrete slabs. At the same time six temporary piles were made, which are used for supporting reinforced concrete slabs at the stage of performing the earthworks for the building shell. At present four more piles are being made.